Editors Note:  On June 9, 2009, PG&E filed with the Federal Energy Regulatory Commission (FERC) a petition to release the Mendocino WaveConnect preliminary permit.

wave-ocean-blue-sea-water-white-foam-photoMendoCoastCurrent, May 11, 2009

In early May 2009, PG&E’s WaveConnect team decided to cancel the Mendocino WaveConnect project because the Noyo Harbor didn’t pass muster and was deemed insufficient in several engineering aspects, therefore unable to support PG&E’s Mendocino WaveConnect pilot wave energy program offshore.

PG&E summarily rejected re-situating the launch site to the Fort Bragg Mill Site, only a short distance from the Noyo Harbor, where PG&E could construct a state-of-the-art launch for Mendocino WaveConnect.

PG&E plans to report their decision to the Federal Energy Regulatory Commission and anticipates surrendering the Mendocino WaveConnect FERC pilot wave energy permit. The City of Fort Bragg, County of Mendocino and the FISH Committee were brought up to speed by PG&E on May 11th.

PG&E had raised $6mm in funding from CPUC and DOE for WaveConnect, allocated to both Mendocino and Humboldt projects. This remaining funds will now be directed to only Humboldt WaveConnect.

And PG&E notes that Humboldt WaveConnect, at Humboldt Bay and its harbor, offers WaveConnect the required spaciousness and the industrial infrastructure as well as a welcoming, interested community.